Q4 Fixture Installs: The Part of Retail Everyone Forgets to Schedule

Retail • Oct 7, 2026

We still see owners schedule construction to the certificate of occupancy and then remember the gondolas. Fixtures, lighting that was in the brand book but not the permit set, and exterior signs each have a clock. On Maui that clock includes the ocean.

Separate the calendars

Construction calendar: walls, MEP, inspections. FF&E calendar: millwork shop drawings, fabric, barge, installers.

If both calendars meet for the first time in November, one of them loses.

  • Shop drawings. Approve them while the walls are still framed.
  • Union or not. Know who is allowed to set fixtures in your center.
  • Power. Islands in the sales floor need floor boxes you already poured.

Stay-open remodels

Phase merchandise. A dark half of the store that looks intentional sells better than a dusty whole store.

JD Pacific Hawaii coordinates GC work with your fixture vendor so we are not arguing over the same hours in the same aisle.

Empty pretty walls are not a store. The fixtures are.

Opening a Maui store before the holidays? Send us both calendars. We will tell you which one is lying.